S.No. |
Name of
Project |
Capacity |
Sponsor |
Year |
|
1. |
Madhavaram, AP |
2x2 MW |
|
2005–06 |
|
2. |
Babbanpur, Punjab |
2x0.5 MW |
Kolta Hydropower Ltd., B-37, Sector – 1, Noida |
2005–06 |
|
3. |
Chakbhai, Punjab |
2x1 MW |
Aqua Power Ltd., B-37, Sector – 1, Noida |
2005–06 |
|
4. |
Ching, HP |
2x0.5 MW |
Hoteshwari Om Power Enterprises Pvt. Ltd., Shimla |
2005–06 |
|
5. |
Manal, HP |
2x1.5 MW |
Himalayan Crest Power Ltd., New Delhi |
2005–06 |
|
6. |
Sahyadri, Karnataka |
1x0.3 MW |
Sahyadri Power Co. Pvt. Ltd., Shimonga, Karnataka |
2005–06 |
|
7. |
Someshwara, Karnataka |
3x8.25 MW |
Pioneer Genco Ltd., Hyderabad |
2005–06 |
|
8. |
Aleo
Manali, HP |
2x1.5 MW |
Aleo Manali Hydro Power Ltd., Noida |
2005–06 |
|
9. |
TB Dam, Karnataka |
3x2.65 MW |
NCL Energy Ltd., Hyderabad |
2005–06 |
|
|
Sugur, Karnataka |
3x1.5 MW |
SLS Power Industries Ltd., Bangalore |
2005–06 |
|
|
Mandegere, Karnataka |
2x1.75 MW |
Bhorukha Power Co. Ltd., Banglore |
2005–06 |
|
|
Chunchi Doddi, Karnataka |
3x3.5 MW |
Sai Purthi Power Pvt. Ltd., Bangalore |
2005–06 |
|
|
Varahi Tail Race, Karnataka |
3x7.5 MW |
M/s Sandur Power Company Ltd., Bangalore |
2005–06 |
|
|
Killa, Punjab |
2x0.875 |
M/s Kotla Power Pvt. Ltd., Noida |
2005–06 |
|
15. |
Lohgarh, Punjab |
2x1 MW |
M/s Aqua Power Pvt. Ltd., Noida |
2005–06 |
|
16. |
Salag, HP |
1x0.15 MW |
M/s Dhauladhar Hydro Systems Pvt. Ltd., Hamirpur |
2005–06 |
|
17. |
Sahoke, Punjab |
1x1 MW |
M/s Kotla Power Pvt. Ltd., Noida |
2005–06 |
|
18. |
RAB Sagar, MP |
2x5 MW |
VA Tech Escher Wyss Flovel Ltd., Faridabad |
2005–06 |
|
19. |
Hemagiri in Karnataka |
4 MW |
Thrishul Power Pvt. Ltd., Hyderabad |
2006–07 |
|
20. |
Somanamaradi SHP Station in Karnataka |
1x6.0 MW |
Narayanpur Power Co. P. Ltd., Banglore |
2006–07 |
|
21. |
Lower Meenmutty SHP in Kerala |
3.5 MW |
KSEB, Kerala |
2006–07 |
|
22. |
Neria SHP in Karnataka |
2x4.5 MW |
Bhorukha Power Co. Ltd., Banglore |
2006–07 |
|
23. |
Khauli HEP in HP |
2x6 MW |
VA Tech Escher Wyss Flovel Ltd., Faridabad |
2007–08 |
|
24. |
Measurements of Head and Discharge at Different Locations of Bassi Power House In HP |
4x15 MW |
HPSEB, Palampur |
|
|
25. |
Marhi Mihi Hydel Power Project in HP |
5 MW |
Marhi Mihi Hydel Power Project, New Shimla |
2007–08 |
|
26. |
Chayadevi SHP Station in Karnataka |
2x12 MW |
Bhorukha Power Co. Ltd., Banglore |
2007–08 |
|
27. |
Ranganadhaswamy Hydro Project in Karnataka |
3x8.25 MW |
Pioneer Power Corp. Ltd., Hyderabad |
2007–08 |
|
|
Kadamne Mini Hydel Scheme-I (KMHS-1) |
2x4.5 MW |
Pashchim Hydro Energy P. Ltd., Hyderabad |
2007–08 |
|
|
MGHE Tailrace Project in Karnataka |
2x11 MW |
Ambuthirtha Power Pvt. Ltd., Banglore |
2007–08 |
|
|
Debal Small Hydro Project in Distt. Chamoli |
2x2.5 MW |
Chamoli Hydro Power Pvt. Ltd., Chamoli |
2007–08 |
|
|
Tuipui SHP Station Distt. Champhai, Mizoram |
2x250 kW |
Amazon Engineering, Aizwal |
2007–08 |
|
|
Sikasar SHP In Chhatisgarh |
2x3.5 MW
|
CSEB, Raipur |
2008–09 |
|
|
Serbari SHP HP |
2x2.5 MW |
Hydrowatt Ltd, Fort,
Mumbai |
2008–09 |
|
|
Drinidhar in HP |
2x2.5 MW |
Lanko Hydro |
2008–09 |
|
|
Baner III |
2x2.5 MW |
Lanko Hydro |
2008–09 |
| 36. |
Akkihebbal Mini Hydel Scheme, Karnataka |
2x2.5 MW |
Cauvery Hydro Energy Ltd., Bangalore |
2008–09 |
| 37. |
Upper Awa Mini Hydel Power Plant in HP |
2x2.5 MW |
Astha Projects Ltd. Hyderabad |
2008–09 |
| 38. |
Patikari Hydro Electric Plant |
|
Patikari Power Pvt. Ltd., Gurgaon |
2008–09 |
| 39. |
Taraila SHP, Chamba (HP) |
2x2.5 MW |
Ginni Global Ltd., New Delhi |
2008–09 |
| 40. |
Loharkhet SHP, Uttarakhand |
4.8 MW |
Parvatiya Power(P). Ltd., Raipur |
2008–09 |
| 41. |
Brahmganga HEP, Kullu (HP) |
2x2.5 MW |
Harisons Hydel Construction Co. Pvt. Ltd., Kullu |
2008–09 |
| 42. |
Sahu SHP in HP |
2x2.5 MW |
Himkailash Hydro Power Pvt. Ltd., Hyderabad |
2008–09 |
| 43. |
Sattegala SHP in Karnataka |
4x1.5 MW |
Bhoruka Power Co. Ltd., Bangalore |
2008–09 |
| 44. |
Nasariganj SHP in Bihar |
2x500 KW |
Bihar State Hydroelectric Power Co. Ltd., Patna |
2008–09 |
| 45. |
Dhelabagh SHP in Bihar |
2x500 KW |
Bihar State Hydroelectric Power Co. Ltd., Patna |
2008–09 |
| 46. |
Hanumanganga Phase-II SHP |
1.95 MW |
Regency Aquaelectro & Motel Resorts Ltd., Paonta Sahib |
2008–09 |
| 47 |
Sidhana HEP, Sangrur |
1x1200 KW |
Kanchanjunga Power Company (P) Ltd. |
2008–09 |
| 48. |
IKU-II SHEP in HP |
2x2.5 MW |
Vamshi hydro Energies Pvt. Ltd., Gurgaon |
2008–09 |
| 49. |
Babehalli HEP in Punjab |
2.7 MW |
Gill Power Gen. Co. Pvt. Ltd., Gurdaspur |
2008–09 |
| 50. |
Toss Mini Hydel Power Project in HP |
2x500 KW |
Toss Mini Hydel Power Project, New Delhi |
2008–09 |
| 51. |
Serlui 'A' SHP |
2x250 + 1x500 KW |
Govt. of Mizoram, Central Block, P&E Office Complex, Aizawl, Mizoram |
2008–09 |
|
52. |
Rani Avanti Bai Sagar |
2x5 MW |
|
|
|
53. |
Upper Khauli SHP |
|
|
|
|
54. |
Toss SHP |
5 MW |
|
|
|
55. |
Loharkhet |
4.8 MW |
Parvatiya Power (P) Ltd., Abhivadan, Panchsheel Nagar, Raipur-492001 (C.G.) |
2008-09 |
|
56. |
Beas Kund SHP |
3x3.0 MW |
Voith Siemens Hydro Pvt. Ltd., Small Hydro A-20 & 21, Sector 59, Noida-201301(UP) |
|
|
57. |
Sainj SHP |
2x2.5 MW |
|
|
|
58. |
Dandela SHP |
13 MW |
Sagar Power (Dandela) Pvt. Ltd., No.396/24, Ooliga Complex, Sampige Road, Malleswaram,Bangalore-560003 |
|
|
59. |
Jyoti SHP |
16 MW |
|
|
|
60. |
Tribeni SHP |
|
|
|
|
61. |
Mussapur SHP in Haryana |
2x700 KW |
Puri Oil Mills Ltd. |
|
|
62. |
Shyang HEP in Himachal Pradesh |
3 MW |
Sai Engineering Foundation Sai Bhawan, Sector – 4, New Shimla |
2009-10 |
|
63. |
Nagavali SHP-Andhra Pradesh |
1.725 MW |
Sardar Power Ltd., 301, Swarganivas Enclave,7-1-619/A, East Srinivas Nagar,Ameerpet, Hyderabad-500038 |
2009-10 |
|
64. |
Samal SHP in Orissa |
5x4 MW |
Andritz Hydro Private Ltd. 49/5, Mathura Road, Village Prithla, Palwal-121 102 (Haryana) |
2009-10 |
|
65. |
Charmadi SHP at Beltthangadi in Karnataka |
2x2.5 MW |
Trinethra Energy Convertions Ltd., “Radhakrishna” No.38, II Main, Defennce Colony, Indiranagar, II Stage, Bangalore-560038 |
2009-10 |